T5 Data Center Hillsboro

Working from developing design documents, Stearns was tasked to commence steel erection on this mission critical project 11 weeks after notification to proceed. Our role included design-assist, sourcing and securing material, structural steel detailing with our in-house crew, and furnishing and installing the structural steel, buckling restrained braces, and roof deck for this 65,500 square foot data center. Total erection time from start to substantial completion was three weeks. We are erecting the structure with our own crews. 

Project Details

Location: Hillsboro, Oregon  

Client: T5

Contractor: Fortis Construction  

Architect: Corgan Associates, Inc. 

Engineer of Record: LA Fuess Partners, Inc.

Size: 65,500 sq. ft.