Port of Portland

Stearns was brought on board early by Skanska USA to supply and install all structural steel components and provide construction services for the complete structure on a critical path schedule. Stearns assisted KPFF Consulting Engineers with design development, construction design, and fabrication for this 7-story, 164,000 sq. ft. office building and parking garage project. Stearns' efforts ensured that the project was completed on time and within budget.

Project Details

Client: Melvin Mark Development

Location: Portland, Oregon

Contractor: Skanska USA

Architect: Zimmer Gunsul Frasca Partnership

Engineer-of-Record: KPFF Consulting Engineers

Size: 164,000 square feet

Number of Levels: 7

Number of Stalls: 350

System Type: Structural Steel

Completion Date: 1998